7 Mar 2025 · Huahui Fire technical team

How to file for fire protection when refitting an office

An office fit-out inevitably means dealing with the relevant government authorities. Collectively, this is known as the project filing (项目报建) stage.

An office fit-out inevitably means dealing with the relevant government authorities. Collectively, this is known as the project filing (项目报建) stage.

If a company's fire protection filing for its office fit-out does not go through, at best the property management company has grounds to refuse the contractor access to site, delaying the programme; at worst the housing and construction bureau (住建局) stops the works and imposes a penalty.

Project filing is quite cumbersome, its timing is hard to control, and it often holds up construction. The person in charge therefore needs to be familiar with the procedure, so that the company can move into its newly fitted-out office sooner.

What is fire protection filing for construction (消防报建/备案)?

Filing for construction (报建) is the process by which the owner or contractor, before carrying out building fit-out works, declares the planned fit-out works to the local construction administration authority as required by national laws and regulations, and obtains approval. Put simply, you tell the relevant authority about your fit-out plans so that it can judge whether the works you are about to carry out are compliant and lawful.

Fire protection filing for construction (消防报建) consists of fire protection filing and approval (消防备案报批) and the application for the construction permit for building works (建筑工程施工许可证). As the state has streamlined administrative procedures in recent years, both are applied for at the same window of the housing and construction authority, approved together and issued at the same time.

Why file for fire protection?

The main reason is safety. Under national rules, offices, restaurants, shops, hotels and similar premises are crowded places (人员密集型的场所). To protect people and property, and to make sure that in a fire people have the opportunity and conditions to escape in time as the national standards require, a company that alters the partitions, sprinklers, smoke extraction or similar in its existing office space must carry out fire protection filing for the office refit (办公室二次装修的消防报建), so that the building's safety remains within the bounds of fire control.

Under current national rules, fit-out works in an existing building with a total investment of RMB 1,000,000 or more, or a floor area of 300 m² or more, must go through fire protection filing and approval and apply for the construction permit at the housing and construction authority before work starts.

If the investment is below RMB 1,000,000, or the fit-out area is below 300 m², filing with the sub-district office (街道) where the project is located is sufficient.

Not every refit needs to be filed, either. The test is whether the fire protection is altered, and you need to determine whether the works are general fit-out works (一般类装修工程) or special fit-out works (特殊类装修工程).

If a leased office still has the previous occupant's fit-out and the incoming company does not change it, the fire filing with the fire authority may remain unchanged.

If it is changed, but the works do not change the main building structure or load-bearing structure, do not change the building's original use, do not alter fire protection systems, do not alter the façade, and involve no other activities that may affect the safety of people's lives and property or the public interest, then they are general fit-out works. Filing is relatively simple, no review of construction drawing design documents (施工图设计文件审查) is needed, and the construction permit can be issued within 2 working days.

But any change to the layout, even one extra partition or meeting room, must be filed for fire protection. These are special fit-out works: any decoration and fit-out activities that may affect the safety of people's lives and property or the public interest, including changes to the main building structure or load-bearing structure, changes of use, alterations to fire protection systems and alterations to the building façade. These works require drawing review and take longer.

The fire protection filing procedure

In general, the process for a company's office fit-out runs roughly as follows:

  1. First, note that the applicant must be the developer (建设单位), not the contractor. The developer applies online in a single "one-stop" process through the Shanghai Construction Project Approval Management System (上海市工程建设项目审批管理系统), under the Shanghai government's "One Network for All Services" (一网通办) portal; there is no need to apply or submit documents in person at a service window.

  2. A qualified design organisation must produce the fire protection design drawings, and the applicant submits the floor plans, electrical drawings and fire protection alteration drawings for the premises (if the fire protection systems are not altered, this can be stated in the remarks).

The drawings comprise: 1) design statement; 2) interior floor plans; 3) ceiling plans; 4) floor finishes plans; 5) electrical drawings; 6) water supply and drainage drawings; 7) air-conditioning drawings; 8) smoke control and extraction drawings; 9) fire protection drawings; 10) fire protection system diagrams. All of these must be ready, otherwise the design drawings will fail review and be sent back for revision.

  1. After obtaining the fire protection design review opinion (消防设计审核意见书), the applicant must apply to the local construction administration authority for the construction permit. During construction, the fire authority will carry out scheduled or unannounced supervisory inspections to ensure construction quality and fire safety. The contractor should cooperate with these inspections and promptly rectify any problems.

  2. During construction, you can also take samples of the construction materials used in the fit-out and send them for testing. Testing must be carried out by a professional fire testing body, which issues a test report. This test report is an important basis for the fire authority's acceptance.

  3. When construction is complete, submit the completion application together with the following acceptance documents:

The developer's application for acceptance (bearing its official seal)

The building works fire acceptance application form (《建筑工程消防验收申报表》), completed by the developer (in duplicate)

The fire authority's building fire protection design review documents for the project (copy)

The fire testing body's test report (original)

Test reports for the fit-out materials listed on the application form (plasterboard, carpet, electrical wire and so on) (copies)

  1. The fire authority will send qualified staff to carry out an on-site inspection, covering mainly the functioning of the fire protection systems, the quality of materials and the compliance of workmanship. If the inspection is passed, the fire authority issues the fire acceptance certificate (消防验收合格证书), marking the completion of the project's fire protection filing and approval process.

Fire protection filing matters a great deal in an office refit. It is the key procedure for making sure the fit-out complies with the relevant regulations and protects public safety. Although the process is cumbersome and complicated, it is an absolutely indispensable part of the fit-out. So before planning an office fit-out, a company must take the time to understand every aspect of filing for the works, and must not overlook this stage, or it may bring itself unnecessary trouble later.

Because many fit-out companies offer fire filing as part of their service, most companies entrust it to them. That calls for extensive experience of fire protection approvals, so as to keep the approval time as short as possible.

Knowing the ins and outs of fire protection filing, and being able to save clients part of the approval costs, has become an essential skill for fit-out companies working on projects in Shanghai.